← Henderson-Vance FYI

Senate Bill 730

The Ratepayer Protection Act and what it means for Vance County.

Citizen-researched. Every claim sourced. Updated June 2026.

Current Status

  • Passed the NC House 69-44 on June 3, 2026.
  • Now in the Senate Rules and Operations Committee for concurrence.
  • Governor Stein has not signed it.
  • Filed by Sen. Steve Jarvis (R-30) and Sen. Buck Newton (R-4). House version led by Rep. Dean Arp (R-Union).

The Provisions

What the Bill Does

These provisions apply to data centers with 100 MW or more of peak monthly demand.

Closed-Loop Cooling Mandatory

Evaporative and open-loop systems are banned. Annual third-party verification required. This directly protects local water supply from large-scale consumption.

15-Year Minimum Utility Contracts

Contracts must include minimum billing requirements, performance provisions, and default protections so costs do not shift to residential ratepayers if a data center scales back or leaves.

Grid Cost Responsibility

Data centers must pay for their own transmission upgrades, new substations, and generation capacity. Residential customers do not subsidize their infrastructure.

Foreign Ownership Ban

Entities tied to China, Russia, Iran, and North Korea cannot acquire, lease, or hold interests in data centers or data center land in North Carolina. Effective December 1, 2026.

Eminent Domain Ban

Cannot use eminent domain to acquire property for data center construction. Private land stays private.

Local Incentives Ban

Local governments cannot offer property tax abatements, PILOTs, grants, or subsidies to data centers above 100 MW. Exception: projects with existing local development approvals.

Environmental and Noise Review

A 500-foot noise study is required. Local governments may also require review of air quality, water, agricultural impact, thermal plumes, parks, and historic sites.

The Gaps

What the Bill Does Not Do

Gap 1: State Tax Exemptions Untouched

NC's data center sales tax exemption program (G.S. 105-164.13(55a)) remains fully intact under SB 730.

  • 37 data centers currently qualify.
  • Current cost: $45 to $57 million per year in foregone revenue.
  • If all planned projects build out: up to $450 million per year.
  • Construction-phase exemptions alone: $1.5 to $2.3 billion.
  • Exempts electricity, servers, hardware, software, HVAC, and construction materials from the ~7% combined state and local sales tax.
  • Qualification: $75M+ investment over 5 years, above-county-average wages, health insurance.
  • No sunset date. NC is one of only 7 states where the exemption never expires.
  • NC is a “dark” state with no centralized reporting of aggregate data center tax break costs.

Sources: EDPNC, NC Dept. of Commerce (April 2026), Good Jobs First, Stateline (April 2026)

Gap 2: The Coal Retirement Block (Section 10)

The NC Utilities Commission cannot authorize retirement of any baseload generating facility above 100 MW until a certificate has been issued for construction of at least 1,000 MW of new nuclear capacity.

  • In practice: Duke Energy cannot retire its remaining coal plants until a nuclear permit is issued.
  • Coal plants run 30% more expensive per MWh than clean energy alternatives.
  • EDF analysis: forces ratepayers to underwrite approximately $128 million per year.
  • Nuclear timeline: Georgia's AP1000 reactors were 7 years behind schedule and $20 billion over budget. South Carolina's AP1000 was never completed. Consumers there are still paying for it.
  • This provision directly contradictsthe bill's “ratepayer protection” name.

Sources: EDF (June 2026), CleanAIRE NC, Canary Media, WFAE

Comparison

The Three Bills Side by Side

FeatureSB 730 (R)HB 1063 (D)HB 1213 (Bipartisan)
SponsorsSen. Jarvis, Sen. Newton; House: Rep. ArpReps. Prather, Johnson-Hostler, Longest, Helfrich + 14 DemsReps. Loftis (R), Ward (R), Harrison (D)
MW Threshold100 MW40 MWNone (all qualifying)
StatusPassed House 69-44, in Senate RulesReferred to House Rules 4/28, stalledIntroduced 4/30, no committee vote
Closed-loop coolingYesYesNo
15-year contractsYesCost-based rates requiredNo
Grid cost responsibilityYesYesNo
Environmental reviewYes, 500 ftYes, DEQ disclosureNo
Foreign ownership banYesNoNo
Eminent domain banYesNoNo
On-site clean energyNoYes, 25% zero-carbonNo
Water use reportingImpliedYes, if over 1B liters/yrNo
State sales tax exemptionUntouchedRepealedRepealed
Local incentives banYes, 100 MW+Yes, 40 MW+Not addressed
Coal retirement blockYesNoNo
CEPS expansionYesNoNo

HB 1213 has strong bipartisan support. House Speaker Tim Moore and Governor Stein have both called for rolling back the electricity exemption. The substance may be folded into the state budget rather than passing standalone. Governor Stein separately proposed phasing out all NC data center tax incentives by 2033.

Fact Check

What Is Actually Driving Your Electric Bill

Data centers are not currently driving rate increases. They represent less than 1%of Duke Energy's peak demand today. The threat is real, but it is forward-looking. Here is what is actually raising your bill right now.

1. Grid Modernization and Capital Investment

Duke's 10-year capital plan: $145 billion company-wide, $75 billion for grid modernization. In NC, $7.7 billion in grid upgrades for the DEC territory alone. This is the primary justification in every rate case filing. The NC Utilities Commission approved a 3-year stepped increase starting January 2024. Cumulative: approximately 14% increase, from $130 to $149 per month for a typical 1,000 kWh customer. The pending 2025 rate case originally asked for 18% over 2 years. Duke lowered it to approximately 11.6% on June 23, 2026, after AG Jeff Jackson pushed back.

Source: Duke Energy rate filings, NCUC, WUNC (June 23, 2026)

2. Coal Ash Cleanup

14 NC sites. Total estimated cost: $8 to $10 billion. After a settlement with the AG's office, ratepayers bear approximately 50% of cleanup costs. Shareholders absorb the other half. This is baked into current rates and will continue for years.

Source: Utility Dive, NCUC filings

3. Fuel Costs (Coal and Gas Pass-Through)

Passed directly to customers via fuel adjustment. No NCUC approval needed. The January 2026 winter storm alone generated $800 million in fuel and purchased power costs Duke is seeking to recover. Coal fuel costs increased approximately 20% from 2018 to 2024.

Source: Duke Energy filings, WFAE, Carolina Journal

Duke projects data centers will reach approximately 10% of total electricity sales by 2030, with approximately 6 GW in the pipeline. Duke's June 23, 2026, rate case revision removed $173.2 million in large-load customer infrastructure upgrades from the residential rate request, acknowledging these costs should not fall on residential ratepayers. The question is not whether data centers will affect your bill. The question is who pays for the infrastructure they require. SB 730 tries to answer that. Section 10 undermines it.

The Gap

Why 100 MW Is Too High

SB 730's 100 MW threshold creates a loophole. A company can split a 300 MW campus into three 99 MW buildings on adjacent parcels, and none of them trigger a single provision in the bill. No cooling mandate, no contracts, no environmental review.

JurisdictionThreshold
FERC RM26-4 (proposed)20 MW
Virginia GS-525 MW
Alabama Power30 MW
HB 1063 (NC, Dem)40 MW
Tennessee HB 1847 (signed May 2026)50 MW
Pennsylvania PUC50 MW / 100 MW aggregate
Texas SB 675 MW
NC SB 730100 MW

86% of utility tariffstracked by the SEPA DELTa database set their threshold below 100 MW. North Carolina's threshold is an outlier.

Source: SEPA DELTa Database, LBNL (January 2025)

Proven Models

How Other States Closed This Loophole

Virginia DEQ (January 2025)

Three-factor aggregation test. Facilities under common control, in the same industrial category, and on contiguous or adjacent property must be treated as a single source. Distance benchmarks: less than 0.125 miles = presumed single source. 0.125 to 0.25 miles = case-by-case. Greater than 0.25 miles = presumed separate.

Source: Hunton Andrews Kurth

Virginia GS-5 Tariff (Effective January 1, 2027)

Explicit “campus aggregation” clause. Geographically proximate facilities are treated as a single load for rate class purposes.

Source: Virginia SCC

Pennsylvania PUC Model Tariff (2026)

Dual threshold. 50 MW individually OR 100 MW in aggregate. One sentence closes the loophole.

Source: K&L Gates

Illinois EPA

5-year temporal lookback. Emissions from the current project must be aggregated with all projects in the current year plus the previous 4 calendar years. Plus a “technical and economic dependency” test. If Phase 2's site plan, financing, and infrastructure all assume Phase 1 exists, it is aggregated with Phase 1.

Source: Trinity Consultants

A Path Forward

What Graduated Regulation Could Look Like

Instead of a single binary threshold where everything under 100 MW is unregulated and everything over is fully regulated, a graduated framework scales requirements with consumption. No single threshold to game. No cliff to exploit.

Universal Requirements (All Data Centers)

RequirementRationale
Closed-loop cooling mandatoryWater supply protection. A 30 MW facility drains the same aquifer per gallon as a 300 MW facility.
Noise study and limits (50 dBA day, 45 dBA night at property line)Data center HVAC, generators, and cooling run 24/7/365. This is permanent, not construction noise.
Annual third-party verification (cooling and noise)Self-reporting invites underreporting.
Foreign ownership banNational security does not scale with megawatts.

Graduated Tiers

TierRequirements
Tier 1 (20 to 40 MW)Water use disclosure, grid upgrade cost transparency, basic environmental notice to county, annual NCUC reporting.
Tier 2 (40 to 60 MW)Plus 5-year minimum utility contract, demand flexibility participation, DEQ environmental disclosure.
Tier 3 (60 to 100 MW)Plus full environmental review (air, water, agriculture, historic sites), 10-year contract, 75% minimum billing, collateral, 25% on-site clean energy.
Tier 4 (100+ MW)Plus 15-year contract, 85% minimum billing, full infrastructure cost responsibility, eminent domain ban.

This framework draws on proven mechanisms from Virginia's GS-5 tariff, Ireland's CRU Connection Policy (the closest existing graduated model), the EU Energy Efficiency Directive, Pennsylvania's aggregate threshold, and Tennessee's HB 1847. It is not theoretical. Every component exists in active law or regulation somewhere.

Anti-Fragmentation

Combined with Pennsylvania-style aggregation (individual OR aggregate threshold), Virginia-style distance tests, and Illinois-style temporal lookback, there is no profitable stopping point just below any tier boundary. Fragmentation does not work when every facility faces universal baseline requirements and aggregate demand triggers higher tiers.

Take Action

What You Can Do

Contact Your Representatives

Tell them to amend Section 10 (the coal retirement block), lower the threshold, add aggregation language, and repeal the state tax exemption. Your voice matters.

Stay Informed

This bill is in the Senate Rules Committee. The next vote could come at any time. Follow the bill status at ncleg.gov.

Share This Page

Every fact on this page is sourced. Share it with your neighbors, your commissioners, your state representative.

Your Representatives

Who to Contact About SB 730

These are the state legislators who represent Vance County. Their contact information is public record. Call, email, or write. Be respectful and specific: ask them to amend SB 730.

NC Senate - District 11

Sen. Lisa S. Barnes

Franklin, Nash, Vance counties

919-715-3030

lisa.barnes@ncleg.gov

NC House - District 7

Rep. Matthew Winslow

Franklin, Vance (partial)

919-715-3032

matthew.winslow@ncleg.gov

NC House - District 32

Rep. Bryan Cohn

Granville, Vance (partial)

919-733-5824

bryan.cohn@ncleg.gov

U.S. House - District 1

Rep. Don Davis

Eastern NC incl. Vance, Warren, Halifax

202-225-3101 (DC) · 252-999-7600 (Rocky Mount)

dondavis.house.gov

Vance County Board of Commissioners

122 Young Street, Suite B, Henderson, NC 27536 · 252-738-2001

NameDistrictPhoneEmail
Carolyn Faines (Chair)1252-433-8018cfaines@vancecounty.org
Valencia Louise Perry2252-432-5577vperry@vancecounty.org
Charisse Fain (Vice-Chair)3252-767-1563cfain@vancecounty.org
Dan Brummitt4252-432-4774dbrummitt@vancecounty.org
Leo Kelly, Jr.5252-767-7957lkellyjr@nc.rr.com
Yolanda J. Feimster6252-431-7579yfeimster@aol.com
Thomas S. Hester, Jr.7252-738-9771tshester@ncol.net

When you call or email, be specific. Ask them to: remove the coal retirement block in Section 10, lower the 100 MW threshold, add campus aggregation language to prevent loopholes, and support HB 1213's state tax exemption repeal. Reference the bill by name: Senate Bill 730.

References

Sources

  1. NC General Assembly, SB 730 Bill Lookup
  2. NC General Assembly, SB 730 Bill Text
  3. NC Newsline, “House fast-tracks data center regulation bill,” June 2, 2026
  4. NC Newsline, “House advances bill to regulate data centers,” June 3, 2026
  5. CBS 17, “NC House passes data center regulation bill”
  6. Carolina Journal, “NC House passes Ratepayer Protection Act”
  7. CleanAIRE NC, “SB 730 fails ratepayers,” June 4, 2026
  8. EDF, “SB 730 forces NC to underwrite $128M/year for Duke's aging coal plants”
  9. NCEJN, “Under the pretense of protection, SB 730 shifts financial risks to North Carolinians”
  10. Center for Progressive Reform, “NC took a step sideways”
  11. WFAE, “NC House passes data center regulation amid coal concerns,” June 4, 2026
  12. Canary Media, “NC bill would prop up coal until new nuclear is approved”
  13. EDPNC, Data Centers Sales and Use Tax Exemptions
  14. Good Jobs First, “Data Center Tax Breaks Becoming Billion-Dollar Budget Sinkholes”
  15. Stateline, “Many states don't report losses from data center tax breaks,” April 2026
  16. WUNC, “Data centers in NC don't pay taxes on supplies or electricity,” April 22, 2026
  17. WUNC, “Gov. Stein proposes phasing out NC's tax incentives for data centers by 2033,” June 15, 2026
  18. WUNC, “NC legislative leaders support rolling back data center sales tax exemptions”
  19. Duke Energy, 2025 DEC and DEP Rate Case
  20. WUNC, “Duke Energy takes rare step of lowering rate request,” June 23, 2026
  21. SEPA DELTa Database
  22. LBNL, “Electricity Rate Designs for Large Loads,” January 2025
  23. Virginia DEQ Clarification 2025-02 (Hunton Andrews Kurth)
  24. Virginia SCC, GS-5 Data Center Initiatives Fact Sheet
  25. K&L Gates, “Pennsylvania PUC Model Interconnection Tariff,” May 2026
  26. Trinity Consultants, “Illinois Data Center Permitting”
  27. Ireland CRU Large Energy User Connection Policy (Philip Lee LLP analysis)
  28. EU Energy Efficiency Directive, Data Centre Reporting
  29. Tennessee HB 1847, signed May 2026
  30. FERC Docket RM26-4, Large Load Interconnection
  31. WRAL, “NC House passes bill to crack down on data centers”
  32. Data Center Knowledge, “NC tests who pays for AI power boom”
  33. Utility Dive, “Duke coal ash cleanup settlement”
  34. WFAE, “Duke Energy plans to raise rates,” April 28, 2026

This page is a citizen education project. It is not funded by any data center company, activist organization, or political campaign. Every claim is sourced. Share it. Print it. Form your own opinion, but form it with the facts in front of you.